This new 6,638 m² school was built using conventional construction methods, including grade beams on piles supporting a two story structure. The project includes modular classrooms to allow for flexibility in classroom management. This new school accommodates up to 900 students for Edmonton’s Public School District. This collaborative design-build project obtained LEED Silver certification.
Contract Value: 21.2 Million
Start Date: March 2015
Completion Date: September 2017